After a full half-century of existence, during
which it had rendered to the progress of the world a service
immeasurably greater than any dreamed of by the most imaginative
of its indomitable builders, the original Panama Railroad was
abandoned to make way for the canal in whose construction it had
been the chief instrument. Its rails were torn up and its roadway
for the greater part of its length disappeared forever beneath the
waters of Gatun Lake.
At the time of its abandonment very little of
the original road except the alignment remained. When the American
canal-builders arrived on the isthmus they found as the
transportation agency of the great task before them a railway that
in every important respect was a quarter of a century behind the
times. Its rails were too light to sustain the weight of modern
locomotives and spoil cars, its culverts and bridges were in the
same condition, and it had only a single track. They began at once
to convert it into a double-track system, with heavy modern rails,
to strengthen or rebuild its bridges and culverts, to equip it
with modern locomotives and cars, and to supply it with an
up-to-date personnel.
When the road was taken over, in
1904, it had about 47 miles of a single track and 26 miles of
siding, with a rolling stock that was virtually worthless. Five
years later the total trackage was 160 miles: 50 miles of main
track, 35 miles of double track, all re-laid with 90 pound rails;
the equipment, thoroughly modem, comprised 150 locomotives, 1,500
freight cars, 50 passenger cars, and 4,000 spoil cars. Over the
main track there passed daily 574 trains, including 160 trains of
spoil cars. The number of passengers carried in 1910 exceeded two
and a quarter millions, the amount of commercial freight exceeded
one and a quarter million tons, and the amount of excavation spoil
over its various tracks was nearly or quite 40,000,000 tons. It
was indisputably the busiest railway, large or small, in the
world.
Fifty-two years after the
original Panama Railroad had been opened to traffic the
construction of the new one was begun. The surveys were made in
1906 and in June of the following year work was begun.
The situation was in striking
contrast with that which had confronted the builders of the
original road. Those brave pioneers had begun their task in a
pest-ridden and barren wilderness through which they must cut
their way foot by foot. They had only hand implements with which
to work, no land habitations save rude huts in swamps and jungles,
no food supply which would be considered tolerable in these times,
for cold storage was unknown, and no accurate medical knowledge
with which to counteract and overcome tropical diseases. The only
road that it was possible for them to build was along the lines of
least resistance, that is, through the river valleys, where the
natural obstacles were the least formidable. They worked
waist-deep in the slimy water of swamp and morass, piling up
slowly the low embankments upon which to place their road-bed, and
compelled to abandon all progress from time to time because of
sickness which incapacitated the entire force. The labor which
they were able to command was of the poorest and most ignorant
quality, for the curse of pestilence was upon the land and
intelligent laborers could not be induced to enter it.
A half-century later what a
marvelous transformation had been wrought! The isthmus had become
a land of health and plenty. The progress in mechanical invention
and in the science of engineering had been so great that such a
thing as an insurmountable natural obstacle to railway
construction no longer existed. There was assembled on the
isthmus, for the construction of the canal, a mechanical equipment
which em-bodied all the latest and most efficient results of
scientific achievement, and which had never been equaled in size
and perfection anywhere else in the world. There was assembled
also a working force of about forty thousand men, trained and
disciplined in construction work, well housed, well fed, and
carefully safeguarded against disease. The railway constructors
had this equipment and this force to draw upon as they desired,
and while the task before them was a formidable one, with such an
agency at their command it was far from being insurmountable.
What they had to do was to
construct a high level railroad through what was mainly a low level
country. They must have the level at all points higher
than the 87 -foot level of Gatun Lake. In building it they must
cross wide and deep valleys and pierce rocky ridges. The valleys
were covered with dense jungle growth and traversed by numerous small
streams. Their ground levels, which were from 20 to 25 feet above
sea-level, proved on examination to be composed of a mass of soft
clay, decomposed wood and vegetation, from 150 to 200 feet in
depth, resting upon a rock foundation. This mass had near the top
a hard stratum of clay and sand from 20 to 30 feet in thickness,
but the space between this crust and the foundation was filled
with soft material. Across these valleys - one of them, that of
the Gatun River, being about three miles in width - huge
embankments to be constructed, ranging in height from 58 to 74
feet. When the weight of these became too great for the crust to
sustain, it pressed that down upon the material beneath and forced
it to the surface on either side. This action added greatly to the
amount material in the embankments, for the upheavals had to be
counterweighted, virtually doubling the width of the foundations, and
the settlement of the ground surface, varying from 25 to 60 feet,
added the distance in each case to the height of the embankment
the center or road-bed line.
Some conception of the magnitude of the task may be formed by the
statement that there were in all 167 embankments, containing a
total of 16,000,000 cubic yards of material, and 164 cuts, the
heaviest varying depth from 60 to 95 feet. The three-mile fill
across the Gatun Valley alone contained 5,000,000 cubic yards of
material, and of the cuts one was 95 feet deep at the highest
point, another 84 feet, another 80 feet, and another, through
solid and very hard rock, 75 feet. It is not surprising, in view
of these formidable obstacles, that the road cost nearly
$9,000,000, or about $200,000 a mile; It had to be constructed
where it was because higher ground could have been reached only by
going outside the Canal Zone and over a much longer distance, and
at a larger expense.
As originally planned, the line
from Gamboa to Pedro Miguel was to run through Culebra Cut on the
berm of the canal, but this route had to be abandoned because of
the slides. It became necessary to run the line around Gold Hill
through a very difficult region, for a distance of 9 1/2 miles, a
change which added $1,200,000 to the cost.
The work was completed and the
road was turned over formally to the Panama Railroad Company on
May 25, 1912, five years after construction began Its length is a
trifle less than that of the old line, the time of construction
was about the same, and its cost about a million dollars greater.
There all comparison ceases. The old line had no embankments worth
mentioning, and only one cut, whose depth was 24 feet. Such a road
as the new line would have been an utter impossibility a
half-century earlier, for its difficulties would have been
insurmountable and its cost, if construction had been attempted,
would have been so tremendous as to be prohibitive.
It is an interesting fact,
worthy of recording perhaps, that the original roadway was laid
with ties of native wood which decayed so rapidly that soon after
the road was open to traffic these were replaced almost entirely
with ties of lignum vitae brought from Cartagena, the
northern province of Colombia. When the old line was torn up these
ties, after being in the ground for a full half-century, were in
almost perfect condition of preservation. Many ties of similar
wood have been placed on the new line, but the greater part of its
road-bed is laid with ties brought from the United States.
During the first two years of
construction the work was in charge of Ralph Budd, chief engineer
of the Panama Railroad. He resigned in September, 1909, and was
succeeded by Lieutenant Frederick Mears, U.S. A., who was in
charge till the road was completed.
The Panama Gateway, by Joseph Bucklin Bishop
Photo Credits and historical data:
Rails to
the Diggings, by Charles S. Small
The Panama Gateway, by Joseph Bucklin Bishop
Panama,- Kanal, Land und Leute, by Lous Wagner
America's Triumph - Panama, by Ralf Emmett Avery
Wilson and Company - Engineers & Architects and Marble Street Studio
George Chevalier - Historian and Contributor
Vicente Pascual - Historian and Contributor